Board Meeting minutes from the July 13, 2022 are now available on our Meetings Page.
Jul 25, 2022 | Project Updates
The Dryden Road Contractor is starting the first lift of HMA Asphalt Paving today, Monday, July 25, 2022, on Dryden Road. The paving operation will start at Van Dyke Road (M-53) and work westerly along Dryden Road. This project includes two (2) lifts HMA Asphalt...
Jul 20, 2022 | Project Updates
Contractor to continue milling operations along Dryden Road. The milling operation started at the east end of the project (near M-53) and will continue working to the west (toward Metamora Village) at select milling locations. Once milling operations are complete,...
Jul 20, 2022 | Project Updates
Contractor has finished the asphalt paving on Hickory Place, from Lapeer Road (M-24) easterly to Lakeshore Drive. Shoulders and restoration will commence next week. After those items are completed, then permanent signs and pavement markings will be completed. ...
Jul 20, 2022 | Project Updates
Asphalt Paving operations for placement of the top course are scheduled for today and tomorrow (Wednesday, July 20 – Thursday, July 21). Please continue to follow the detour or seek alternate routes for the safety of the construction crew. After the asphalt...
Jul 14, 2022 | Employment
Lapeer County Road Commission, 820 Davis Lake Road, Lapeer, MI 48446 is accepting applications for a Truck Operator. Full time position requiring possession of a CDL Group A. Detailed job descriptions and applications are available on our Employment Page. Interested...
Jul 14, 2022 | Board Meetings
Board Meeting Minutes from the June 29, 2022 our now available on our Meetings page.
Jul 11, 2022 | Project Updates
The first lift of asphalt is complete along Hunters Creek Road, Lapeer Road (M-24) to Morris Road. This week the road will have intermittent road closures for tree removal. Please follow the posted detour or seek alternate routes for the safety of the crew. Once...
Jul 11, 2022 | Project Updates
Line painting for the 2022 Pavement Marking Program will resume Wednesday, July 13, 2022. Crews started line work last Thursday and Friday. To finish the remaining roads scheduled for paint this summer, it is expected to take another three (3) working days. Line...