2022 Clifford Road HMA Overlay Project

Clifford Road, Village Limits easterly to Cargill Road (County Line), in Burlington Township, will be under construction for HMA (Hot-Mix Asphalt) paving overlay.  Project will include, but is not limited to, Culvert replacement, milling pavement joints and intersections at curb lines, placing asphalt overlay, gravel shoulders, traffic signs and pavement markings.  Road will be closed to traffic (buses, emergency vehicles and garbage trucks will be able to access the road).  Paving Contractor will have traffic control regulators present while working.  Expect uneven pavement after culvert replacement, milling operations and between paving of the westbound and eastbound lanes.  Watch Facebook and our website for schedule updates.

Update – it is expected that the schedule of this project will be pushed to approximately October 2022.  More updates to follow when date is closer.

Funding source(s): Primary Rd Heavy Maint

Location of roadwork:

Clifford Road - Village Limits easterly to Cargill Road (County Line)

Burlington

When is the work being done:

Fall 2022

Description of work:

Asphalt Overlay

Impact on Traffic:

Closed to Through Traffic During Construction

Latest Updates

No items found
Receive Updates on the Project
Subscribe to Project Updates

Project Contact

Destain Gingell, PE

Advisories & Detours