Contractor, Ace Saginaw Paving, will start Work on Rochester Road, Dryden Road north to Sutton Road, on Tuesday, May 10, 2022 (weather permitting).  This work will include milling the existing asphalt at intersections and existing curb line locations, pavement of HMA (asphalt) paving, aggregate shoulders, traffic signs and pavement markings.  Road will be closed to through traffic, Download Detour Map, (buses and emergency vehicles will have access to the roadway).  Contractor will have traffic control regulators present while working.  Expect uneven pavement after milling operations and between paving the northbound and southbound lanes.  Following schedule is for information only.  Please watch our Facebook page and our website for schedule updates.

  • Tuesday, May 10 – Milling Pavement
  • Wednesday – Saturday, May 11 – 14 – Paving Operations
  • Week of May 23 – Placement of Aggregate (Gravel) Shoulders and Driveway Approaches
  • June – Placement of final pavement markings