May 26, 2022 | Uncategorized
Oregon Road, Elba Road easterly to Indian Road, will close next week for ditching and culvert replacements. It is anticipated that the existing asphalt will be crushed, in preparation for new asphalt placement, the week of June 13, 2022. Continue to watch the Lapeer...
May 26, 2022 | Project Updates
The Contractor is scheduled to resume HMA (asphalt) overlay paving on Lake Pleasant Road, Burnside Road northerly to North Branch Road (M-90). Weather depending, the paving will start the first week of June. Continue to watch the Lapeer CRC Facebook Page and website...
May 26, 2022 | Project Updates
The Contractor is scheduled to resume HMA (asphalt) overlay paving on Burnside Road, Lapeer Road (M-24) easterly to Fish Lake Road. Weather depending, the paving will start the first week of June. Continue to watch the Lapeer CRC Facebook Page and website for...
May 26, 2022 | Project Updates
Genesee Road Bridge over Hasler Creek project, between Elba Road and Maple Leaf Road, is scheduled to start Tuesday, May 31, 2022. This section of roadway will be closed to through traffic, including emergency vehicles. Please use Detour Route for the duration of...
May 26, 2022 | Uncategorized
Due to predicted poor weather this weekend, the paving of Maple Leaf Road at the Box Culvert is rescheduled to the first week of June. Continue to watch the Lapeer CRC Facebook Page and the Website for project updates.
May 26, 2022 | Uncategorized
Due to predicted poor weather this weekend, the paving of Mitchell Road Bridge Approaches is rescheduled to the first week of June. After the asphalt is placed, the Contractor will schedule the guardrail installation and final restoration. Continue to watch the...
May 19, 2022 | Project Updates
The Lapeer CRC Contractor will start milling operations along Lake Pleasant Road, from Burnside Road northerly to North Branch (M-90) Road on Friday, May 20, 2022. The removal of the existing asphalt in select locations is being done in preparation of the placement...
May 19, 2022 | Project Updates
The Lapeer CRC Contractor will start milling operations along Burnside Road, from Lapeer Road (M-24) easterly to Fish Lake Road on Friday, May 20, 2022. The removal of the existing asphalt in select locations is being done in preparation of the placement of a HMA...
May 12, 2022 | Project Updates
Project Update! Culvert replacements are planned to be completed on Lake Pleasant Road on this Thursday for upcoming HMA (asphalt) overlay project. The temporary gravel culvert crossings will have asphalt patches placed starting Saturday (weather dependent). Please...