Burnside Road Contractor is scheduled to finish the eastbound lane and approach paving today, Thursday, June 9, 2022. Aggregate shoulders and approaches are scheduled to be completed during the week of June 13, 2022. Restoration of topsoil, seed and mulch will be placed after shoulders are complete. Please continue to follow the posted detour until the project is completed for the safety of the work crew. It is anticipated that all work will be completed by June 30, 2022, depending on weather. Continue to watch the Lapeer CRC Facebook page and our website for further updates.
Recent Posts
Archives
- February 2025
- January 2025
- November 2024
- September 2024
- July 2024
- June 2024
- April 2024
- March 2024
- February 2024
- January 2024
- December 2023
- November 2023
- October 2023
- September 2023
- August 2023
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- October 2021