Lake Pleasant (N) Road Contractor (Burnside Road north to M-90) is scheduled to pave the road and approaches from Monday, June 13 to Thursday, June 16, 2022, weather dependent.  Aggregate shoulders and driveway approaches are scheduled to be completed after the asphalt paving operations are completed.  Restoration of topsoil, seed and mulch will be placed after shoulders are complete.  Please continue to follow the posted detour until the project is completed for the safety of the work crew.  It is anticipated that all work will be completed by June 30, 2022, depending on weather.  Continue to watch the Lapeer CRC Facebook page and our website for further updates.