2022 Daley Road HMA Overlay Project

Daley Road, Lapeer Road (M-24) easterly to  Fish Lake Road, in Mayfield Township, will be under construction for HMA (Hot-Mix Asphalt) paving overlay.  Project will include, but is not limited to, Culvert replacement, milling pavement joints and intersections at curb lines, placing asphalt overlay, gravel shoulders, traffic signs and pavement markings.  Road will be closed to traffic (buses, emergency vehicles and garbage trucks will be able to access the road).  Paving Contractor will have traffic control regulators present while working.  Expect uneven pavement after culvert replacement, milling operations and between paving of the westbound and eastbound lanes.  Watch Facebook and our website for schedule updates.

Funding source(s): Primary Rd Heavy Maint

Location of roadwork:

Daley Road - Lapeer Road (M-24) easterly to Fish Lake Road

Mayfield

When is the work being done:

Summer 2022

Description of work:

Asphalt Overlay

Impact on Traffic:

Closed to Through Traffic

Latest Updates

June 14, 2022 Daley Road Paving This Weekend

Daley Road will be closed to thru traffic later this week for Asphalt Paving Operations on Friday and Saturday (June 17 – 18, 2022).  Please seek alternate routes, or follow the posted detour for the safety of the construction crew.  Shoulder material will be placed after paving operations is complete, schedule to be determined.  Between the paving and shoulder operations, the aggregate shoulder grade / elevation will be lower than the roadway.  Continue to watch the Lapeer CRC Facebook page for schedule updates as they occur.

June 9, 2022 Daley Road Milling to Start Friday

The Lapeer CRC Contractor will start milling operations along Daley Road, from Lapeer Road M-24 easterly to Fish Lake Road, on Friday, June 10 to Saturday, June 11, 2022.  The removal of the existing asphalt in select locations is being done in preparation of the placement of a HMA Asphalt Overlay.  The milling operations will be completed under Traffic Regulator’s Flag Control – Expect Delays in this area Friday/Saturday or seek alternate route.  The date for the placement of the asphalt overlay is not scheduled at this time.  Continue to watch the Lapeer CRC Facebook page and the website for schedule updates as they are known.

May 12, 2022 Daley Road Culvert Asphalt Patches to Start Friday

Project Update!  Culvert replacements have been completed on Daley Road for the upcoming HMA (asphalt) overlay project.  The temporary gravel culvert crossings will have asphalt patches placed starting Friday.  Please expect minor delays on Daley Road, M-24 to Fish Lake Road, as the gravel is removed and asphalt placed in the crossings.  Continue to follow us on Facebook and our Website for more schedule updates.

Receive Updates on the Project
Subscribe to Project Updates

Project Contact

Destain Gingell, PE

Advisories & Detours