No one will be able to get through including emergency vehicles. (Bridge will be out, closed to everyone). Detour signs will go up June 10, 2021, structure removal will start week of June 14th. Project is anticipated to be completed by the end September (tentative a steel and material delivery dates) Bridge rehabilitation work includes replacing deck, clean and paint steel beams, Substructure extension and approach work on Saginaw Road over the south branch of the Flint River.
Funding source(s): Rural Task Force Funding
Location of roadwork:
Saginaw Road will be closed at bridge over S. Branch of Flint RiverWhen is the work being done:
June 14th - end of SeptemberDescription of work:
Bridge RehabilitationImpact on Traffic:
Saginaw Road will be closed at bridge over S. Branch of Flint RiverLatest Updates