Jun 1, 2023 | Project Updates, Uncategorized
Update: Bids have been received, after review of the 2023 HMA Primary Road Overlay program budget, two (2) of the projects have been identified for postponement. It is anticipated that Lake Pleasant Road (I-69 north to Imlay City Road) and Pratt Road (Washburn Road...
Jun 30, 2022 | Project Updates
Top course paving work will be complete tonight, however road will remain closed Friday, July 1, 2022 for Approach paving work. After approaches are complete, Lake Pleasant Road will be open for the Holiday Weekend. The road will re-close on Wednesday, July 6, 2022...
Jun 29, 2022 | Project Updates
Paving operations on Lake Pleasant Road, from Imlay City Road north to Lum Road, will resume Thursday, June 30, 2022. This mornings rain has postponed the paving operations today. Crews will be back tomorrow, weather depending, to completed the top course of...
Jun 14, 2022 | Project Updates
Lake Pleasant Road, from Burnside Road northerly to M-90, will be under construction to continue with placement of Shoulder Aggregate (gravel) on Thursday and Friday (June 16 – 17, 2022) this week. Roadway paving operations are completed. Once shoulder...
Jun 14, 2022 | Project Updates
Lake Pleasant Road, from Imlay City Road to Lum Road will be closed to thru traffic on Saturday, June 18, 2022, for the first lift of Asphalt Paving Operations. Please seek alternate routes, or follow the posted detour for the safety of the construction crew. The...
Jun 9, 2022 | Project Updates
The Lapeer CRC Contractor will start milling operations along Lake Pleasant Road, from Imlay City Road northerly to Lum Road on Friday, June 10 to Saturday, June 11, 2022. The removal of the existing asphalt in select locations is being done in preparation of the...
Jun 9, 2022 | Project Updates
Lake Pleasant (N) Road Contractor (Burnside Road north to M-90) is scheduled to pave the road and approaches from Monday, June 13 to Thursday, June 16, 2022, weather dependent. Aggregate shoulders and driveway approaches are scheduled to be completed after the...
May 19, 2022 | Project Updates
The Lapeer CRC Contractor will start milling operations along Lake Pleasant Road, from Burnside Road northerly to North Branch (M-90) Road on Friday, May 20, 2022. The removal of the existing asphalt in select locations is being done in preparation of the placement...